Project Update: Mesa, Rodriguez and Riveria Homes
28 Jan
Mesa House:
Exterior doors and security bars for the windows have been installed.
Luis Ruiz, a local from Puerto Penasco has applied stucco to the interior side and exterior of the cinderblock walls. He and his family are working towards qualifying for a house next year.
The stucco will be painted later this spring by Volunteers from the states.
The rough plumbing is all installed and in an hour or so all the eletrical will be complete. Four electricians from Hogan Electric in Salt Lake City along with a local, Abram Martinez, are wiring the house.